If $20$ workers can build a wall $30$ m long in $25$ days, how many workers are needed to build a similar…
If $20$ workers can build a wall $30$ m long in $25$ days, how many workers are needed to build a similar wall $48$ m long in $20$ days?
- $36$
- $40$
- $42$
- $48$
Solution
Workers $\propto$ length (direct) and $\propto \dfrac{1}{\text{days}}$ (inverse). $w = 20 \times \dfrac{48}{30} \times \dfrac{25}{20} = 20 \times \dfrac{48 \times 25}{30 \times 20} = 20 \times 2 = 40$.