$20$ men can complete a piece of work in $30$ days, working $9$ hours daily. How many men are required to…

$20$ men can complete a piece of work in $30$ days, working $9$ hours daily. How many men are required to finish a job that is $\dfrac{2}{3}$ as large in $20$ days, working $6$ hours daily?
  1. $24$
  2. $28$
  3. $30$
  4. $36$

Solution

Original work units $= 20 \times 30 \times 9 = 5400$ man-hours. New job size $= \dfrac{2}{3} \times 5400 = 3600$ man-hours. So $m \times 20 \times 6 = 3600 \Rightarrow m = \dfrac{3600}{120} = 30$ men.

Asked in: IMO

Practice more DIRECT AND INVERSE PROPORTIONS questions on Aicharya