A software company sets up $m$ number of computer systems to finish an assignment in 17 days. If 4 computer…
A software company sets up $m$ number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of $\mathrm{m}$ is equal to: